Construction News

Wed July 03 2024

Related Information

Crossrail photos reveal tunnelling progress

1 Mar 13 Crossrail has released new photos showing tunnelling beneath the capital.

Work is continuing around-the-clock in several underground locations work to create 26 miles (42km) of tunnels beneath London.

Five tunnelling machines are now in operation – Phyllis and Ada in west London, Elizabeth and Victoria in east London, and Sophia in Plumstead, southeast London

Together the five machines have created more than 3 miles (5km) of tunnels so far with nearly 500m built in the single biggest week of tunnelling to-date

In the western tunnels alone, Phyllis has put more than 1,500 tunnel rings in place between Royal Oak and Park Lane at the edge of Hyde Park.

The western tunnelling machines will pass through the new Crossrail station at Bond Street this month followed by Tottenham Court Road and Farringdon later this year, while the eastern tunnelling machines will break through into Canary Wharf station box this spring.

Tunnelling is also underway beneath four central London station sites using sprayed concrete lining techniques – Bond Street, Tottenham Court Road, Liverpool Street and Whitechapel. Sprayed concrete lining will be used to build a total of 12km of platform tunnels and cross passages at stations along the Crossrail route.

Sprayed concrete lining is also under way at the 34.5m deep Stepney Green shaft in east London - one of Europe’s largest underground caverns. The works are to allow the two eastern tunnelling machines to pass through the shaft later this year on their way to Farringdon via Whitechapel and Liverpool Street.

Crossrail’s sixth and seventh tunnel boring machines will begin further tunnelling work in Plumstead and Pudding Mill Lane later this year.

Refurbishment works are under way at the 135-year-old Connaught Tunnel in southeast London, which will be brought back into use for Crossrail. A section of the Royal Docks will shortly be drained to allow major works later this year to open the tunnel from above for the first time since its construction in 1878.

Crossrail chief executive Andrew Wolstenholme said: "With 26 miles of new tunnels to be built for Crossrail we are delivering our own London marathon beneath the streets of the capital. This is a huge and complex task with work underway 24 hours a day below London’s streets but our first few miles of tunnel are now completed. These new underground images show the scale of transformation taking place beneath London and the essential new transport links being created with every metre of new tunnel built.”

Crossrail has five tunnelling machines now in operation – Phyllis and Ada in west London, Elizabeth and Victoria in east London, and Sophia in Plumstead, southeast London.

26 miles of tunnels are being built as Crossrail moves into peak tunnelling period. Together the five machines have created more than 5km of tunnels so far.

The western tunnelling machines will pass through the new Crossrail station at Bond Street this spring followed by Tottenham Court Road and Farringdon later this year.

Related Information

Elizabeth and Victoria, the eastern tunnelling machines, launched in 2012 on their journey towards Farringdon. Elizabeth will break through into Canary Wharf station box this spring.

This is the Hanover Square ticket hall tunnels at Bond Street station.

Tunnelling is now underway beneath four central London station sites using sprayed concrete lining techniques – Bond Street, Tottenham Court Road, Liverpool Street and Whitechapel.

Crossrail's Finsbury Circus worksite underground - a network of tunnels is under construction beneath Finsbury Circus as part of the Liverpool Street station works.

Finsbury Circus again.

Whitechapel access tunnels.

Stepney Green access shaft is one of Europe’s largest underground caverns and large enough to fit 100 double decker buses. The works are to allow the two eastern tunnelling machines to pass through the shaft later this year on their way to Farringdon via Whitechapel and Liverpool Street.

Refurbishment works at the 135-year-old Connaught Tunnel in southeast London will enable it to be brought back into use for Crossrail.

A section of the Royal Docks will shortly be drained to allow major works later this year to open the Connaught tunnel from above for the first time since its construction in 1878.

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »