Construction News

Thu August 01 2024

Related Information

Inquiry starts into £870m Northern Line extension

20 Nov 13 The public inquiry into the proposed £870m extension of London Underground’s Northern Line from Kennington to Battersea began this week.

It is expected to run for four weeks.

The inquiry, called for by the secretary of state for transport, is part of the Transport & Works Act Order (TWAO) process. As part of that procedure, a breakdown of estimated costs has been produced (see below).

The independent inspector will consider evidence that has been submitted by Transport for London, individuals and organisations with an interest in the project. If planning powers are obtained from the government, and funding secured, then construction of the Northern line extension could begin in 2015 with new stations at Nine Elms and Battersea Power Station opening in 2020.

Estimate of costs

  • Surveying, drilling and soil sampling: £531,769
  • Acquisition of land and rights over land: £23,105,372
  • Earthworks (including land reclamation and landscaping): £319,061
  • Fees of professional and other advisers, in connection with the implementation of the project once authorised: £20,236,085
  • Tunnels and bridges: £289,193,582
  • Highway works, including alterations to and relocation of existing services and statutory undertakers’ apparatus: £2,127,074
  • Permanent way or other supporting/guiding structures:  £76,160,566
  • Workshops, depots, stations and other buildings: £285,092,193
  • Electrical plant and equipment: £43,167,471
  • Signalling and communications: £43,167,471
  • Vehicles: £68,378,149
  • Alteration, modification and removal of existing works: £16,811,263
  • Total: £868,290,056

Got a story? Email news@theconstructionindex.co.uk

MPU
MPU

Click here to view latest construction news »