Working on RAF Aircraft Hanger

8 May We have been working on a RAF Aircraft hanger, removing two large areas of concrete to form doorways to accept new doors. We needed to break out two areas of concrete each measuring 3.0m x 3.0m and 400mm deep.

Working on RAF Aircraft Hanger

Step 1: Track Sawing

We cut form the perimeter of the 3.0m x 3.0m opening using the Tryolit WSE Track Saw.

Step 2: Stitch Drilling

We then stitch drilled the corners with the Husqvarna DM 340 Drill Rig and Motor. This was to prevent overcutting at the end of the cuts.

Step 3: Breaking Out

We were then ready to break out the concrete using Demolition Robot Husqvarna DXR145.